Assessing the substrate
Existing plaster in dry areas can often be tiled onto directly if it is sound, dry and free of flaking paint, checked by tapping across the surface for hollow patches. Anything hollow or soft gets cut back to solid material.
In wet areas, particularly around a shower or bath, plaster is not enough on its own. We use tile backer board, either cement-based or foam-cored, fixed to studwork or over existing plasterboard, because it gives a stable, water-tolerant base that will not swell or delaminate.
Stud walls being rebuilt as part of a refurbishment are boarded with backer board from the outset rather than standard plasterboard behind any tiled area.
Priming and preparing the surface
Backer board joints are taped and filled with a proprietary jointing compound so the board reads as one continuous flat surface. Highly absorbent or dusty substrates, including some plasters and old render, get a coat of primer to control suction so the adhesive cures evenly rather than drying too fast at the surface and too slow underneath.
Any existing tiles being tiled over, which is sometimes viable on a sound, flat wall, are keyed and primed with a specialist bonding primer rather than tiled onto directly.
Choosing the adhesive class
Adhesive is not a single product. Classes under the EN 12004 standard tell you what it can be trusted to do, and using the wrong one is a common cause of tiles coming loose.
| Class | What it means | Typical use here |
|---|---|---|
| C1 | Standard cementitious adhesive | Dry areas, small/standard format ceramic |
| C2 | Improved, higher bond strength | Most bathroom walls, larger tiles |
| C2T | Improved with reduced slip | Wall tiling generally, prevents slump before curing |
| C2TE S1 | Improved, reduced slip, flexible | Wet areas, large-format porcelain, over backer board |
Setting out before fixing a single tile
We measure the wall and dry-lay or mark out the tile positions before mixing any adhesive, working out from a level datum line rather than starting in a corner. The aim is to avoid slivers of cut tile at an eye-level edge and to keep cuts balanced on both sides of a feature such as a niche or window.
Tile spacers keep joint widths consistent, typically 2-3mm for rectified large-format porcelain and slightly wider for pressed ceramic with a more irregular edge. A laser level or spirit level checks both the horizontal course lines and that the first row is genuinely level, since an out-of-level starting row throws every tile above it out gradually.
Fixing, grouting and finishing edges
Adhesive is combed onto the wall and, for large-format tiles, back-buttered onto the tile itself to achieve full coverage and avoid voids that later crack under pressure or let water track behind the tile. Tiles are tapped in and checked for lippage as they go rather than corrected after the adhesive sets.
Once cured, typically around 24 hours, joints are grouted with a CG2 waterproof grout in wet areas. Internal corners and the junction between wall and bath or tray are left ungrouted and finished with silicone sealant instead, because these are movement joints that rigid grout would eventually crack.
Where to read next
Questions we get asked most
Can you tile straight onto plasterboard in a shower area?
Not on its own. Wet areas need a water-tolerant board such as cement or foam-cored tile backer board, or a proper tanking membrane over the plasterboard first.
Why does tile spacing matter so much?
Consistent joint width is what makes a wall look properly finished. It also gives grout enough width to do its job without cracking under movement.
What is back-buttering and is it always needed?
It means applying adhesive to the back of the tile as well as the wall. It is standard practice for large-format and porcelain tiles to guarantee full coverage underneath.
Should grout or silicone go in the corners?
Silicone, not grout. Corners and junctions with the bath or tray move slightly over time, and rigid grout will crack there while flexible sealant will not.
How long before I can use the shower after tiling?
Allow the adhesive and grout to cure fully, and the sealant to skin over, before regular use. This typically takes several days in total, and we will confirm exact timings for the products used on your job.